Case study · Instant payments
Instant payments can now carry $10 million. Which wires should move?
FedNow and RTP both allow payments of up to $10 million, 24 hours a day, every day. This case study shows how a US bank can move the right business payments from wires to instant, safely, in about six months.
The situation
For years, a business payment above $1 million had one fast option: the wire, with cut-off times and no weekend service. That has changed quickly.
- February 2025. The Clearing House raised the RTP network limit from $1 million to $10 million.
- June 2025. FedNow raised its limit from $500,000 to $1 million and added account activity thresholds, so banks can set dollar and speed limits by customer segment.
- November 12, 2025. FedNow raised its network limit for customer credit transfers from $1 million to $10 million.
- 2025 to 2026. FedNow handled 8.41 million transactions in 2025, then 2.73 million worth $271 billion in the first quarter of 2026.
Instant payment limits went up 20 times in under three years
Network limit per payment, in US dollars
Each bank can still set lower limits for its own clients.
The Federal Reserve points to real-estate transactions, vendor payments and corporate payroll as new uses. Each bank still sets its own, lower limits based on its risk appetite.
What it means for a bank
Products
Instant supplier payouts, real-estate closing funds, payroll funding and treasury moves for commercial clients.
Limits and risk
Tiered limits by client segment and history, not one number for everyone.
Liquidity
Funding settlement 24/7, including weekends and holidays, and watching intraday positions.
Fraud and sanctions
Payments are final in seconds, so screening, payee checks and fraud scoring must finish in real time.
Operations
Exceptions, investigations and client support outside business hours.
Data
ISO 20022 messages carry richer remittance data that clients can reconcile automatically.
When money can move
Hours open per day, US Eastern time. Fedwire opens at 9 p.m. the evening before each business day and closes at 7 p.m.
Bank holidays close the wire too; FedNow and RTP stay open.
The approach: six months from wires to instant
Month 1
Find the wires that should move
Analyse 12 months of outgoing domestic business wires by amount, time sent, purpose and client. Good candidates: supplier payments, real-estate closings, payroll funding and wires sent after cut-off. Keep cross-border and the largest treasury flows on the wire for now.
Months 1 to 2
Pick one MVP use case
For example, same-day supplier payouts for existing commercial clients, up to an agreed limit, in the channel they already use. Agree the success measures before building.
Month 2
Design limits, liquidity and controls
Limit tiers by segment, velocity thresholds, dual approval above a set amount, real-time sanctions screening, and a weekend liquidity plan agreed with treasury.
Months 3 to 4
Build and test
Test each limit tier at, just below and just above the boundary; duplicate and replayed payments; rejects and returns; weekend and holiday settlement; screening response time under load; fraud rules on first-time payees; ISO 20022 data mapping and reconciliation files; and falling back to the wire if the rail is down.
Month 5
Launch in waves
Start with pilot clients and low limits, run a penny test in production, and raise limits only after each review.
Month 6 onward
Run and grow
Review volumes, fraud, exceptions and liquidity every week, then add the next use case.
Wire or instant? The decision path
How a business payment is routed once instant is live for a client
If any answer is no: send by wire, or hold for review
Risks and controls
| Risk | Why it matters | Control |
|---|---|---|
| Authorised push payment fraud | An instant payment cannot be recalled once sent | Payee checks, step-up or a hold for first-time payees, client education |
| Slow sanctions screening | A slow check blocks a payment that must settle in seconds | Real-time screening with response-time targets and a tested fallback |
| Weekend liquidity shortfall | Settlement continues when treasury desks are closed | Pre-funded positions, balance alerts, on-call treasury |
| Wrong limit for a client | Too high invites fraud; too low sends clients back to wires | Tiered limits reviewed every month |
| Operations gaps | Exceptions arrive at night and at weekends | A 24/7 rota or vendor support, with runbooks |
Numbers to watch
Watch next: the Fedwire release planned for November 2026 now lands in November 2027; the Federal Reserve plans to open Fedwire on Sundays (22 hours a day, six days a week) around 2028 or 2029; and a proposed Regulation J change would let banks send FedNow payments through intermediary banks. Details are on the Instant Payments tracker.
Sources
- Federal Reserve Financial Services: FedNow limit raised to $10 million, Nov 12, 2025
- ABA Banking Journal: FedNow risk feature and $1 million limit, Jun 2025
- ABA Banking Journal: banks can set lower limits
- Digital Transactions: new uses and the RTP limit increase
- Crowdfund Insider: FedNow volumes and participants
- Instant Payments and ISO 20022 Tracker
Get the case studies as a PDF, free
Take this case study and the other two with you, to share with your team.
- All three case studies with charts, plans, risks and controls (14 pages)
- Plus the Cloud vs On-Prem study of 29 US banks (10 slides)
Enter your email and confirm it. The download links arrive straight away.
I use your email to send the case studies and, now and then, payments insights. Nothing is sold or shared. Every email has a one-click unsubscribe link, and you can ask me to delete your details at any time at sp@paymentconsultant.top. Didn’t receive it? Check your spam folder, or email me and I’ll send it personally.
Want this plan for your bank or fintech?
I help banks and fintechs launch and change payment products safely: discovery, delivery plans, testing, release and go-live.
Book a 15-minute callOpen the instant payments trackerIndustry case study built from public sources and my payments delivery experience. It does not describe any client engagement. Figures are as published by the sources listed; general guidance, not legal advice.