Case Study: $10 Million Instant Payments

FedNow and RTP now allow $10 million payments around the clock. A six-month plan for a US bank to move the right business payments from wires to instant, safely.

← All case studies

Case study · Instant payments

Instant payments can now carry $10 million. Which wires should move?

FedNow and RTP both allow payments of up to $10 million, 24 hours a day, every day. This case study shows how a US bank can move the right business payments from wires to instant, safely, in about six months.

$10MFedNow network limit since Nov 12, 2025
$10MRTP network limit since Feb 2025
24/7settlement, including weekends and holidays
1,500+financial firms on FedNow in 2026

The situation

For years, a business payment above $1 million had one fast option: the wire, with cut-off times and no weekend service. That has changed quickly.

  • February 2025. The Clearing House raised the RTP network limit from $1 million to $10 million.
  • June 2025. FedNow raised its limit from $500,000 to $1 million and added account activity thresholds, so banks can set dollar and speed limits by customer segment.
  • November 12, 2025. FedNow raised its network limit for customer credit transfers from $1 million to $10 million.
  • 2025 to 2026. FedNow handled 8.41 million transactions in 2025, then 2.73 million worth $271 billion in the first quarter of 2026.

Instant payment limits went up 20 times in under three years

Network limit per payment, in US dollars

FedNow at launch, Jul 2023$500K
FedNow, Jun 2025$1M
RTP, Feb 2025$10M
FedNow, Nov 12, 2025$10M

Each bank can still set lower limits for its own clients.

The Federal Reserve points to real-estate transactions, vendor payments and corporate payroll as new uses. Each bank still sets its own, lower limits based on its risk appetite.

What it means for a bank

Products

Instant supplier payouts, real-estate closing funds, payroll funding and treasury moves for commercial clients.

Limits and risk

Tiered limits by client segment and history, not one number for everyone.

Liquidity

Funding settlement 24/7, including weekends and holidays, and watching intraday positions.

Fraud and sanctions

Payments are final in seconds, so screening, payee checks and fraud scoring must finish in real time.

Operations

Exceptions, investigations and client support outside business hours.

Data

ISO 20022 messages carry richer remittance data that clients can reconcile automatically.

When money can move

Hours open per day, US Eastern time. Fedwire opens at 9 p.m. the evening before each business day and closes at 7 p.m.

MonTueWedThuFriSatSunWire22h22h22h22h19hClosed3hInstant24h24h24h24h24h24h24h
Open all dayOpen most of the dayOpen brieflyClosed

Bank holidays close the wire too; FedNow and RTP stay open.

The approach: six months from wires to instant

Month 1

Find the wires that should move

Analyse 12 months of outgoing domestic business wires by amount, time sent, purpose and client. Good candidates: supplier payments, real-estate closings, payroll funding and wires sent after cut-off. Keep cross-border and the largest treasury flows on the wire for now.

Months 1 to 2

Pick one MVP use case

For example, same-day supplier payouts for existing commercial clients, up to an agreed limit, in the channel they already use. Agree the success measures before building.

Month 2

Design limits, liquidity and controls

Limit tiers by segment, velocity thresholds, dual approval above a set amount, real-time sanctions screening, and a weekend liquidity plan agreed with treasury.

Months 3 to 4

Build and test

Test each limit tier at, just below and just above the boundary; duplicate and replayed payments; rejects and returns; weekend and holiday settlement; screening response time under load; fraud rules on first-time payees; ISO 20022 data mapping and reconciliation files; and falling back to the wire if the rail is down.

Month 5

Launch in waves

Start with pilot clients and low limits, run a penny test in production, and raise limits only after each review.

Month 6 onward

Run and grow

Review volumes, fraud, exceptions and liquidity every week, then add the next use case.

Wire or instant? The decision path

How a business payment is routed once instant is live for a client

1Domestic business paymentClient sends from online banking or an API
2Within the client’s instant limit?Tier set by segment and history
3Payee checked, screening passed?Fraud score and sanctions in seconds
4Send instantFinal in seconds, 24/7

If any answer is no: send by wire, or hold for review

Risks and controls

RiskWhy it mattersControl
Authorised push payment fraudAn instant payment cannot be recalled once sentPayee checks, step-up or a hold for first-time payees, client education
Slow sanctions screeningA slow check blocks a payment that must settle in secondsReal-time screening with response-time targets and a tested fallback
Weekend liquidity shortfallSettlement continues when treasury desks are closedPre-funded positions, balance alerts, on-call treasury
Wrong limit for a clientToo high invites fraud; too low sends clients back to wiresTiered limits reviewed every month
Operations gapsExceptions arrive at night and at weekendsA 24/7 rota or vendor support, with runbooks

Numbers to watch

Wires moved to instantShare of eligible wires now sent instantly
Payment success rateAccepted and settled on the first try
Fraud lossesPer $1 million sent, against the wire baseline
Time to creditSeconds from send to beneficiary credit
ExceptionsPer 10,000 payments, by type
Client adoptionPilot clients using instant each month

Watch next: the Fedwire release planned for November 2026 now lands in November 2027; the Federal Reserve plans to open Fedwire on Sundays (22 hours a day, six days a week) around 2028 or 2029; and a proposed Regulation J change would let banks send FedNow payments through intermediary banks. Details are on the Instant Payments tracker.

Sources

Get the case studies as a PDF, free

Take this case study and the other two with you, to share with your team.

  • All three case studies with charts, plans, risks and controls (14 pages)
  • Plus the Cloud vs On-Prem study of 29 US banks (10 slides)

Enter your email and confirm it. The download links arrive straight away.

I use your email to send the case studies and, now and then, payments insights. Nothing is sold or shared. Every email has a one-click unsubscribe link, and you can ask me to delete your details at any time at sp@paymentconsultant.top. Didn’t receive it? Check your spam folder, or email me and I’ll send it personally.

Want this plan for your bank or fintech?

I help banks and fintechs launch and change payment products safely: discovery, delivery plans, testing, release and go-live.

Book a 15-minute callOpen the instant payments tracker

Industry case study built from public sources and my payments delivery experience. It does not describe any client engagement. Figures are as published by the sources listed; general guidance, not legal advice.